Does MineSched support variable processing recovery as user parameters for correct calculation of final metal output from the processing plant. My MineSched paramters setting are as below:
- Input parameters
- Define Geology – Metal quality as Aggregate
- Define Geology – User Parameters – Initial processing recovery REC is 0.86
- Define Geology – User Calculation – Metal_Output = Metal * REC
- Set Schedule – Location – Stockpile with parameters with same initial REC = 0.86
- Schedule parameters tab with the changed REC at a specific date on start date of year 2038.
- Define Geology – Metal quality as Aggregate
- Results
- REC check = Metal_output / Metal added to Mill
- REC check = Metal_output / Metal added to Mill
- Review
- The results make me confused about how to set up correct variable processing recovery parameters to generate correct metal_output results in MineSched.
- My double-check of the results convince me that the REC settings in Stockpile will not change even we give a changed REC in schedule parameters tab with date /event.
- Seek Help from Geovia MineSched Team.
- please help to check if I made mistakes to sestup the variable REC parameters or there is a better way to achieve this objective.